1531 Utah
Construction of a 6 Story Industrial Flex Building in the SODO Area of Seattle, Washington.
Friday, December 19, 2008
SNOW DAYS
Wednesday, December 17, 2008
Aerial Photo as of 12/15/08
Tuesday, December 16, 2008
The training begins...
Ray has now mastered how to wear a hardhat correctly.
The system works!
Preparing a dewatering system
Seattle to the North on a typically rainy day
Concrete being dumped into the pump truck
It takes alot of space to build this project
Looking South at the adjacent City Light Substation
Looking South the the BNSF Rail Container Loading Yard
Arent' you guys glad that they fired Ty.
The completed base of the crane.
Footings ready to pour along the South Wall
The Art of Steel...Nice work Pacer
Hey guys.....
View of the West Core
Midway thru the pour on the East Core
My work looks good
We take the humans out before we are done
Only 500 yards to go on this pour
Another perspective
Another grove of steel pipe at the back elevator core
The BEAST
Look..It can fly
Ouch!
"I hope it doesnt land on my foot"
We find this is easier standing up
The training starts.....
We like Stoneway too!
Cadman is on the Job
100 plus truckloads to pour the East elevator core
Thursday, December 4, 2008
A very measured approach
Thats it! The gloves are coming off
Rod-Buster tying wire
Concrete Truck Driver working up a sweat
Frank from AESI inspecting work
Welding Table
This is where two pipes are welded together prior to being driven
Garth conducting the DeWitt crew
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)
Followers
Blog Archive
►
2012
(4)
►
June
(1)
►
May
(2)
►
April
(1)
►
2009
(62)
►
October
(1)
►
July
(8)
►
June
(13)
►
May
(6)
►
March
(21)
►
January
(13)
▼
2008
(64)
▼
December
(63)
SNOW DAYS
Aerial Photo as of 12/15/08
The training begins...
Ray has now mastered how to wear a hardhat correctly.
The system works!
Preparing a dewatering system
Seattle to the North on a typically rainy day
Concrete being dumped into the pump truck
It takes alot of space to build this project
Looking South at the adjacent City Light Substation
Looking South the the BNSF Rail Container Loading ...
Arent' you guys glad that they fired Ty.
The completed base of the crane.
Footings ready to pour along the South Wall
The Art of Steel...Nice work Pacer
Hey guys.....
View of the West Core
Midway thru the pour on the East Core
My work looks good
We take the humans out before we are done
Only 500 yards to go on this pour
Another perspective
Another grove of steel pipe at the back elevator core
The BEAST
Look..It can fly
Ouch!
"I hope it doesnt land on my foot"
We find this is easier standing up
The training starts.....
We like Stoneway too!
Cadman is on the Job
100 plus truckloads to pour the East elevator core
A very measured approach
Thats it! The gloves are coming off
Rod-Buster tying wire
Concrete Truck Driver working up a sweat
Frank from AESI inspecting work
Welding Table
Garth conducting the DeWitt crew
Nick gets Nicked
Freight Elevator Core
Looking to the West
Ken is all Smiles
Brian and Karen having fun in the Mud
Steel Piles waiting to be cut down to size
Mike with NW Construction showing the way
Mac and Matt monitoring Soil Condtions
First section of the Crane Base is being prepared
Footing Mat for the Crane Base
The Pile Driver's First Blow
DeWitt's Crew is on top of things
He is serious about boring holes.
Dont mess with my Trackhoe
ABI pouring the first footing walls
All American Pumper
A lot going on
Pile Driver's are strong dudes
Mac Daddy is the sheriff in town
Using Modern Day methods to move a 100' pipe
The first pile being raised off the ground
Ron on his machine
NW Construction is hard at it
The first batch of 270 piles that are 100' each in...
►
November
(1)
About Me
1531 Utah LP
View my complete profile